Scrum vs. Traditional Project Management
Traditional project management emphasizes on conducting detailed upfront planning for the project with emphasis on fixing the scope, cost and schedule - and managing those parameters. Whereas, Scrum encourages data-based, iterative decision making in which the primary focus is on delivering products that satisfy customer requirements.
To deliver the greatest amount of value in the shortest amount of time, Scrum promotes prioritization and Time-boxing over fixing the scope, cost and schedule of a project. An important feature of Scrum is self-organization, which allows the individuals who are actually doing the work to estimate and take ownership of tasks.
Following table summarizes many of the differences between Scrum and traditional project management:
Parameters | Scrum | Traditional Project Management |
---|---|---|
Emphasis is on | People | Processes |
Documentation | Minimal - only as required | Comprehensive |
Process style | Iterative | Linear |
Upfront planning | Low | High |
Prioritization of Requirements | Based on business value and regularly updated | Fixed in the Project Plan |
Quality assurance | Customer centric | Process centric |
Organization | Self-organized | Managed |
Management style | Decentralized | Centralized |
Change | Updates to Productized Product Backlog | Formal Change Management System |
Leadership | Collaborative, Servant Leadership | Command and control |
Performance measurement | Business value | Plan conformity |
Return on Investment | Early/throughout project life | End of project life |
Customer involvement | High throughout the project | Varies depending on the project lifecycle |
SCRUM increases ROI
One of the key characteristics of any project is the uncertainty of results or outcomes. It is impossible to guarantee project success at completion, irrespective of the size or complexity of a project. Considering this uncertainty of achieving success, it is therefore important to start delivering results as early in the project as possible. This early delivery of results, and thereby value, provides an opportunity for reinvestment and proves the worth of the project to interested stakeholders. It is important to:
Some of the key differences with respect to Value-driven Delivery in Scrum project and Traditional projects are given in the figure below.
In Scrum projects, User Stories are ranked in order of priority which is an effective method for determining the desired User Stories for each iteration or release of the product or service. The purpose is to create a simple, single list with the goal of prioritizing features, rather than being distracted by multiple prioritization schemes.
This simple list also provides a basis for incorporating changes and identified risks when necessary. Each change or identified risk can be inserted in the list based on its priority relative to the other User Stories in the list. Typically, new changes will be included at the expense of features that have been assigned a lower priority.
Minimum Marketable Features (MMF) are also defined, so that the first release or iteration happens as early as possible, leading to increased ROI.